Ongoing Enhancements at Highpointe Condominium
At Highpointe Condominium, we are committed to continuous improvement, ensuring our residents enjoy the pinnacle of comfort and style.
Surveillance System
Upgrade
In-house
$5,700.00
July 30th, 2025
Upgraded access controls for resident safety and peace of mind.
Elevator Systems Repair
Repair/Upgrade
ELCON
TBD
TBD
Repairs on the malfunctioning elevator mechanical brakes and electronic control systems to ensure safe and reliable operation. Maintenance will also be performed on the elevator doors to address alignment and performance issues. Additionally, a preliminary review will be conducted to evaluate potential modernization options to improve long-term functionality and meet current code requirements.
Done Projects
Each month, we usefully close our projects. Here is the list of our recently closed ones.
HVAC Expansion Tank Replacement
Replacement
In-house
$2,600.00
July 18th, 2025
The existing expansion tank was found to be severely rusted and leaking, compromising the performance and safety of the HVAC system. The tank was removed and replaced with a new, properly sized unit. All piping connections were secured and tested to ensure leak-free operation, restoring proper system pressure and reliability
Boiler #2 Partial Rebuild
Rebuild/Repair
In-house
$7,113.00
July 18th, 2025
Boiler #2 had a cracked section that was replaced approximately one year ago by the previous contractor. A new 700 lb section was delivered to the boiler room, and six boiler sections were rebuilt with the new section installed. The boiler successfully passed the hydrostatic test twice following the repair.
Boiler #1 Full Rebuild
Rebuild
In-house
$14,900.00
June 14th, 2025
Boiler #1 was out of service during the 2024/2025 heating season due to multiple leaks. A complete disassembly of the 17-section boiler was performed, followed by thorough cleaning and a full rebuild. The boiler successfully passed the hydrostatic test twice after the repair.
Ground Water Management
Regular Maintenance
In-house
$1,300.00
June 03th, 2025
Implementation of effective solutions to prevent flooding in the loading dock area, ensuring sustainable drainage and a stable environment.
Pool and Spa Renovations
Service/Managment
AquaSafe
$27,500.90
May 20th, 2025
Professional resurfacing to rejuvenate the pool and spa areas, providing a fresh, durable, and modern finish that enhances both aesthetics and safety.
HVAC ISO-Valves Tier 2-7
Service/Install
In-house
$1,500.00
April 28th, 2025
The existing isolation valves for HVAC tiers 2 through 7 were either heavily rusted or completely inoperable, making it impossible to isolate these tiers for necessary in-unit HVAC repairs or replacements. New isolation valves were installed to restore full control and functionality, allowing proper maintenance and servicing of the HVAC systems across these tiers.
HVAC System Condenser Pump
Repair/Rebuild
In-house
$290.00
May 8th, 2025
A 2-year-old condenser pump began to overheat and produce excessive noise during operation. The pump was fully disassembled, thoroughly cleaned, and rebuilt using new replacement parts. After reassembly, the pump was tested and confirmed to be operating properly and quietly.
Pest and Rodent Treatment
Service/Managment
Orkin
$6450.00
April 4, 2025
A comprehensive pest and rodent control treatment was carried out across the entire building to address ongoing issues reported by residents. The treatment included interior and exterior inspection, baiting, sealing of entry points, and targeted extermination methods. This proactive approach ensures a healthier living environment and aims to prevent future infestations through ongoing monitoring and follow-up treatments as needed.
Sewer inspection/jetting
Service
In-house
$1,100.00
March 30th, 2025
Comprehensive sewer inspection and jetting to ensure clear, efficient pipelines. Prevent blockages, improve flow, and maintain a reliable drainage system.
Building-wide access update/control
Service/Managment
In-house
$874.00
March 30th, 2025
Upgrade building-wide access control for enhanced security and convenience. Implement advanced systems for seamless entry management and improved safety.
Fire Pump rebuild
Service/Managment
In-house
$940.00
March 6th, 2025
This project involved the full rebuild of a critical fire pump system for our facility. The original contractor estimate for the job was $5,400. However, by sourcing parts independently and coordinating repairs with in-house resources, we successfully completed the rebuild at a significantly reduced cost of $940. This initiative not only restored the pump to full operational condition but also resulted in substantial cost savings while maintaining compliance with safety and operational standards.
Building Exhaust Fan Repair
Service/Repair
In-house
$1240.00
January 15th, 2025
Out of the 10 exhaust fans, only one was operational. As most units were original to the building, all fans were disassembled and thoroughly inspected. New motors and bearings were installed, and electrical connections were repaired to restore full functionality.
Garage Light Repair
Service/Repair
In-house
$2400.00
December 23th, 2024
The project involved a complete rewiring and rebuilding of the existing electrical system. All outdated components supporting old fluorescent lamps were removed and replaced with modern LED light fixtures. Timers were installed to ensure efficient operation of the lighting system, helping the community reduce unnecessary electricity expenses.
"Keep on going, and the chances are that you will stumble on something, perhaps when you are least expecting it. I never heard of anyone ever stumbling on something sitting down."